October 6th, 2026

Eighty panels are scheduled to be formed and poured across multiple dates over the next two months. Note how full of steel (rebar) the walls are - in some cases, using the fattest made. This is required to support the weight of multiple floors and the roof structurally.

Please pray for dry weather when "pour days" are scheduled for concrete. If it is too wet, this will push the schedule out.